The French State has identified a new site as suitable for the 'fast track' procedure, and extended the capacity reservation for an existing site
To support the State's re-industrialisation and digital sovereignty strategy and strengthen its attractivity to high-power industries, the French NRA (the Commission de regulation de l’énergie – CRE) approved a specific procedure on 7 May 2025 for the rapid connection of very high-power consumption facilities on suitable sites.
In accordance with the conditions outlined in Article 1.4.3 of the Technical Reference Documentation (Article_1.4.3 fr), the French State has asked RTE to pre-reserve 700 MW of capacity at the "Grande Industrie" area of the "Grand Port Maritime de Dunkerque" (Bourbourg, Nord, Hauts-de-France).
This pre-booking is valid for up to nine months from 15 December 2025 and can be extended by up to three months if a land allocation selection process is ongoing at the end of the nine months.
The State has also asked for an extension of the A GW capacity pre-booking at the ZAC du Bosquel site in the commune of Le Bosquel in the Somme department (Hauts-de-France). This pre-booking, which initially was supposed to end on 16 february 2026, is thus extended for three more months.
The pre-reserved capacity is immediately reserved and will be taken into account in the exploratory studies and technical and financial proposals (and not accepted), which are affected by this reservation.

December 19, 2025